Y-12: DESIGN
Oak Ridge: Clinton
(1942-1943)
Events: The Uranium
Path to the Bomb, 1942-1944
Although the Lewis Report had placed gaseous
diffusion ahead of the electromagnetic
approach, many were still betting in early 1943 that Ernest
Lawrence (right) and his "calutron"
would eventually predominate.
Lawrence and his laboratory of mechanics at the University
of California, Berkeley, continued to experiment with the giant 184-inch cyclotron
magnet, trying to reach a consensus on which shims, sources, and collectors to
incorporate into the Y-12 Electromagnetic Plant
that was to be built
at Oak Ridge.
Research on magnet
size and placement and beam resolution led
Lawrence and his group in fall 1942 to propose an arrangement of huge
electromagnetic coils connected by a bus bar in an oval racetrack
configuration, as seen from above. Forty-eight
gaps in the racetrack between the coils would each contain two vacuum
tanks. With two racetracks per building, ten buildings would be necessary
to provide the estimated 2,000 sources and collectors needed to separate
100 grams of uranium-235 daily. The Berkeley researchers hoped
that improvements in calutron design, or placing multiple sources and
collectors in each tank, might increase efficiency and reduce the number
of tanks and buildings required, but experimental results were
inconclusive even as Stone & Webster of Boston,
the Y-12 contractor at Oak Ridge, prepared to break ground.
At a meeting of Leslie Groves
(right), Lawrence, and
John R. Lotz of Stone & Webster in Berkeley late in December 1942, Y-12
plans
took shape. It was
agreed that Stone & Webster would take over
design and construction of a 500-tank facility, while Lawrence's laboratory
would play a supporting role by supplying experimental data. By the time
another summit conference on Y-12 took place in Berkeley on January 13 and 14,
Groves had persuaded the Tennessee Eastman Corporation to sign on as plant
operator and arranged for various parts of the electromagnetic equipment to be
manufactured by the Westinghouse Electric and Manufacturing Company, the
Allis-Chalmers Manufacturing Company, and the Chapman Valve Manufacturing
Company. General Electric agreed to provide electrical
equipment.
On January 14, after a day of presentations and a demonstration of the
experimental tanks, Groves stunned the Y-12
contractors by insisting that the first racetrack of ninety-six tanks be in
operation by July 1 and that 500 tanks be delivered by year's end. Given
that each of the five planned racetracks was 122 feet long, 77 feet wide and 15
feet high; that the completed plant was to consist of three 450-feet long
buildings, each housing two racetracks placed end-to-end on the second floor;
that tank design was in flux; and that separate chemistry buildings also would
be needed for preparing charge materials and separating uranium recovered from
the tanks, Groves's demands were little less than shocking. Nonetheless, Groves maintained that his
schedule could be met.
For the next two months Lawrence, the contractors, and the Army negotiated
over the final design. While all involved could see possible improvements,
there simply was not enough time to incorporate every suggested
modification. Y-12 design was finalized at a March 17 meeting in Boston,
with one major modification -- the
inclusion of a second stage of the
electromagnetic process. The purpose of this second stage was to take the
enriched uranium-235 derived from several runs of the first stage and use it as
the sole feed material for a second stage of racetracks containing tanks
approximately half the size of those in the first. Groves approved this
arrangement and work began on both the Alpha (first-stage) and Beta
(second-stage) tracks.

Click
here to view sources and notes for this page.