HANFORD BECOMES OPERATIONAL
Hanford Engineer Works
(1943-1944)
Events: The Plutonium
Path
to the Bomb, 1942-1944
The plutonium production facilities at the Hanford
Engineer Works took shape with the same wartime urgency as did the uranium
facilities at Oak Ridge. In
February 1943, Colonel Matthias returned to the location he
had helped select the previous December and set up a temporary
headquarters. In late March, Matthias received his assignment. The three
water-cooled production reactor (piles),
designated by the letters B, D, and F, would be built about six miles apart on
the south bank of the Columbia
River. The four
chemical
separation plants would be built in pairs at two sites nearly ten miles south of
the piles. A facility to produce slugs and perform tests would be
approximately twenty miles southeast of the separation plants near Richland. Temporary quarters for construction workers would be put up
at the Hanford town site, while permanent facilities for other personnel would be located down
the road in Richland, safely removed from the production and separation
plants. Life at Hanford would soon
come to resemble that of the other "atomic
boomtowns" of the Manhattan
Project, Los Alamos and Oak Ridge.
Ground-breaking for the water-cooling plant for the B Reactor, the westernmost
of the three, took place on August 27, 1943. Construction also began that
summer on the two chemical separation locations (200-West and 200-East).
The facilities there were to be massive, scaled-up versions of those associated with
X-10
at Oak Ridge, each containing separation and concentration buildings in addition
to ventilation (to eliminate radioactive and poisonous gases) and waste storage
areas. Labor shortages and the lack of final blueprints, however, soon forced DuPont to
stop work on the 200 areas and concentrate on
the construction of support facilities in the B Reactor area (100-B). As a result, the 1943 progress on chemical separation was
limited to the digging of two very large holes in the ground.
Not
until October 10 did DuPont engineers drive the first stakes marking the
location of the B-Reactor pile building. The area immediately under
the pile was excavated and carefully load-tested. Once the
foundations were fixed, work gangs began to lay the first of 390 tons of
structural steel, 17,400 cubic yards of concrete, 50,000 concrete blocks,
and 71,000 concrete bricks that went into the pile building. By
early 1944, a windowless concrete monolith towered 120 feet above the
desert. Assembly of the pile itself began in February.
The cast-iron base and the thermal and biological shields around the pile
were completed by mid-May. It took another month to lay the graphite
blocks within the shield and install the top shield and two months to wire
and pipe the pile and connect it to various monitoring and control
devices. By
July 1944, not only was the B Reactor nearing completion, but the second (D)
reactor was about halfway finished as
well. Work on the third (F) reactor had not yet begun. To test several new technologies, a
smaller
test pile was constructed at Hanford and began operations in March of
1944.
In
January 1944, workers laid the foundations for the first chemical
separation building, T Plant located in 200-West. Both the T Plant
and its sister facility in 200-West, the U Plant, were completed by
October. (U Plant was used only for training during the Manhattan
Project.) The separation building in 200-East, B Plant, was
completed in February 1945. The second facility planned for 200-East was
canceled. Nicknamed Queen Marys by the workers who built them, the
separation buildings were awesome canyon-like structures 800 feet long, 65
feet wide, and 80 feet high containing forty process pools. The
interior had an eerie quality as operators behind seven feet of concrete
shielding manipulated remote control equipment by looking through
television monitors and periscopes from an upper gallery. Even with
massive concrete lids on the process pools, precautions against radiation
exposure were necessary and influenced all aspects of plant design.
Given how new all of these technological systems were,
no one knew
whether they would work as anticipated. Excitement mounted at Hanford as the date for the first operation of
a plutonium production reactor approached. On September 13, 1944, Enrico
Fermi placed the first slug into the pile at B Reactor. Final checks
on the pile had been uneventful. The scientists could only hope they were
accurate, since once the reactor was operational the intense radioactivity would
make maintenance of many components impossible. Loading slugs and taking
measurements lasted two weeks. From just after midnight until approximately
3:00 a.m. on September 27, the pile ran without incident at a power level higher
than any previous fission chain reaction (though only at a fraction of design
capacity). The operators were elated, but their excitement turned to
astonishment when the power level
began falling after three hours. It fell continuously until the pile
ceased operating entirely on the evening of the 28th. By the next morning,
the reaction began again, reached the previous day's level, then
dropped.
Hanford scientists were at a loss to explain the pile's failure to maintain a
chain reaction. Only the
foresight of DuPont's engineers made it possible to resolve the crisis.
The cause of the strange phenomenon proved to be xenon
poisoning, wherein xenon (a fission by-product) gradually built-up and
absorbed neutrons that were needed to sustain the chain reaction.
With shutdown, the xenon decayed, neutron flow resumed, and the pile started up
again.
Fortuitously, despite the objections of some scientists who complained of
DuPont's excessive caution, the company had installed a large number of extra
tubes. This design feature meant that the pile in B Reactor could be expanded to
reach a power level sufficient to overwhelm the xenon poisoning. Success
was achieved when the first irradiated slugs were discharged from B Reactor on
Christmas Day, 1944. The irradiated slugs, after several weeks of storage,
went to the chemical separation and concentration facilities. By the end
of January 1945, the highly purified plutonium underwent further concentration
in the completed chemical isolation building, where remaining impurities were
removed successfully. Los Alamos
received its first plutonium from Hanford on February 2. While it was
still by no means clear that enough plutonium could be produced for use in bombs
by the war's end, Hanford was by early 1945 in operation. Only two years
had passed since Matthias first set up his temporary headquarters on the banks
of the Columbia River.
To view the next "event"
of the Manhattan Project, proceed to "1942-1945:
Bringing It All Together."

Click
here to view sources and notes for this page.